Minutes of HERA Meeting 27.09.2005
HERA
B.Holzer summarized HERA operation of last week
( transparencies)
- HERA operation was quite efficient. There were no serious problems.
About 1 pb-1/fill was achieved in 2 fills. The proton current,
80 - 100mA in 150 bunches, was increased by improving the performance
of the pre-accelerator chain. The electron current was
increased in small steps from 28 to 38mA. The injection efficiency
is quite high for both beams. New injection files were made.
- Technical problems: High temperatures at a cavity window SR caused
several beam dumps. The power of the transmitter was reduced.
The cavity window will be replaced in the winter shut-down.
This morning there was a break due to defective temperature
sensors SR and SEDAC alarms of beam position monitors.
The power glitch on Sunday morning was observed on all 3 power stations.
Polarization, M.Vogt ( transparencies)
- The beam energy and first order harmonic bump scans were done.
The 2nd order scan are almost done. 50% polarization was
achieved with pilot bunches. This indicates that there is no large
polarization asymmetry for different rotator settings.
The proton bunch intensities, 600 - 700 muA, are quite high.
Polarization of the colliding bunches is reduced by beam beam effects.
The electron tunes were reduced until the H1 electron background
started to increase.
- An energy fine scan will be done in the next days.
ZEUS
Y.Yamazaki summarized the ZEUS status ( transparencies)
- In general, running conditions were quite good. Proton spikes appeared
in recent fills. The last fill was excellent.
- The data taking efficiency was good for the first half of the week.
It was rather poor over the weekend due to problems with the
CTD readout and calorimeter power supplies. The CTD HV has been
stable.
- The calorimeter is presently closed all the time because of problems
with the calorimeter breaks. The ZEUS shift crew should be
called in case of problems during injection or proton ramping or
when the injection procedure is changed.
- The access next week is needed for work on the calorimeter.
H1
J.Olsson summarized the H1 status ( transparencies)
- The background conditions are fine. The normalized fast track trigger
rate is below the goal. Last week the HV efficiency was 83%, the best
value of this running period.
- An delivered integrated luminosity of 200pb-1 is still reachable if the
present rate of luminosity production continues.
HERMES
A.Miller summarized the HERMES status
- The running conditions were good. The electron background was very low.
The proton background was relatively high, some triggers had to be
pre-scaled.
- The lumi studies (beam scans) have not been done. The scans are still
pending.
- The maintenance day next week is not needed, although it was planned to
exchange the dissociator tube.
Schedule
- Continue luminosity operation. Increase electron current.
- The maintenance day next Wednesday will be as usual, i.e. stop
beam operation at 06:00hrs. Access to the tunnel will be possible
until 14:00hrs. All interlocks should be set by 22:00hrs.
The NEG pumps in the north and souths IRs will not be regenerated.
ZEUS is the coordinating experiment.
Uwe Schneekloth