Minutes of HERA/Experiment Coordination
Meeting 11.01.2005
Agenda
- Brief status reports HERA and experiments
including
- Polarization working group
- LPOL cavity and calorimeter
- Shutdown plans
Status and milestones of shutdown preparation
- Spare magnet situation
- H1 FST/BST repair
- ZEUS STT repair
- HERMES Recoil detector
- Schedule and operation
- Date of next meeting
- AoB
Minutes:
- In December HERA started luminosity operation with 60 bunches. By the
end of December the vacuum conditions were sufficiently good
to increase the number of bunches to 120.
- The startup after the Christmas break was a bit slow due to several
technical problems. Operational statistics for 2005 so far:
45% faults, 26% luminosity operation.
- Operations improved last week. It is now possible to inject 80mA protons
and about 34mA electrons. 82mA, record proton current per bunch,
was accelerated to 920GeV. This would correspond to 123mA with 180
bunches. The beam currents were reduced somewhat due to the background
conditions at H1 (last fill 65mA proton, 26mA electron current).
The integrated luminosity of last week was 3.7pb-1. This is better
than the average in 2004, in spite of the maintenance day on Wednesday.
- Last week the vacuum in the north IR was not improving anymore.
The NEG pumps
were therefore regenerated on Wednesday.
- Background spikes appeared again on the weekend. Two magnet power
supplies are under suspicion: GA08 N30 causing large spikes and
QQ24 OR229
rather frequent spikes. The QQ24 chopper will now be exchanged.
The current leads of the magnet will be checked. In general, fine
tuning of the machine is necessary to improving the background
conditions. The present backgrounds might be related to the very
high specific luminosity and small proton emittance.
- Progress on polarization tuning has been slow, maximum polarization
around 30%. The usual procedures
have been used, energy scan and harmonic bumps. Polarization was
drifting during recent fills. It is not clear what is changing.
The plan is to repeat tune and energy scans in the second half
of a fill.
- So far there no difference in the lifetime between electrons and
positrons.
- The proposal is to continue luminosity operation with 120 bunches,
increasing the electron current as possible, until the background
conditions have improved. Increase to 180 bunches in February.
- There was no news on the production status of the spare BU coils.
This should be checked.
- In general, ZEUS is running fine. The detector has been operational
since 27.12. During the holidays the delivered integrated luminosity
was 700nb-1, 500nb-1 were taken. Recently, there were very nice
luminosity fills. The proton background tuning is still slow.
- The general level of proton background is fine, although higher and
more fluctuating that in Aug. 2004. The electron background is fine.
Sometimes there is some direct synchrotron radiation which needs to
be tuned away.
- ZEUS proposes to increase the electron current to the maximum H1 can
tolerate. If necessary HERA should go to 180 bunches.
- Recently there were two major power cuts in the hall. The first one
was due to unannounced maintenance of the smoke detection system.
The second was caused by a fake gas and evacuation alarm.
It always takes several hours to recover from power cuts. In addition
several electronics components break. The situation was discussed
with the technical emergency group. Tests of the safety system are
only allowed if the technical coordinator of the experiment and
HERA is informed in advance.
- The design of the FDET removal fixture is well advanced. The plan
is to remove the FDET, in order to tighten the seal of the solenoid
insulation vacuum and to improve the cooling, without removing the
GO and GG magnets. Two engineers from Oxford University will act
as external reviewers. The HERA coordinator will also be involved
in the review. The final decision, whether the FDET will be removed
during the shutdown, will be taken in mid June. The length of the
shutdown would be 7 weeks.
- The detector is ready for data taking with all components operational.
The background is improving. The proton gas background decreased by
a factor 4.5 after repairing the leaks NR6 and NL14 and activation
of the NEG pumps in December. Another factor 1.5 was gained after
NEG regeneration last week. During the last fill the BToF rate
was below 50 kHz, which is safe for HV operation. A rate of 100 kHz is
the limit for long term operation without radiation damage of the
CIP electronics.
- The background is dominated by proton gas interactions. Safe operation
is possible at IexIp = 20x60mA**2 under quiet beam conditions.
A factor 4 improvement is needed for safe operation
at design currents. The present data is unusable for many physics
analysis. NEG pumps should be regenerated again at the next occasion.
H1 would like to stay with 120 bunches.
- Regular proton spikes make chamber operation even more difficult.
Spikes seem to be correlated with the GA08 magnet in the north and
QQ24 magnet in the east. The large proton spikes must be cured.
Otherwise H1 cannot take physics data.
- The horizontal and vertical vertex positions were shown. After moving
the detector by 7mm in early December the distance of C5a and C5b
to the electron beam is now the same as to the positron beam in
the previous running period. The interaction point is 7mm too high in
H1. During the last shutdown an asymmetric keyhole C5b was
installed to compensate for this.
- The FST repair and BST modifications are proceeding as planned. The
goal is to be ready by June (FST) and August (BST). A milestone will
be the test of the radiation hard APC chips end of February. The
preferred date (end of August) and length (6 weeks) of the shutdown
is unchanged.
- Data taking restarted 29.12.04. The spectrometer is fully operative.
Maintenance work was performed during the access last week. The LPol
calorimeter was reinstalled.
- The target had several problems: leak in the oxygen pipe, possible
leak in the cooling water system and broken RF generator for the ABS.
Everything was repaired. The quartz glass tube is more reliable than
the pitex tube. It will be replaced at every monthly access.
End of fill running, presently starting at 10mA, is very successful.
- The electron background conditions are excellent. High background,
up to 2MHz spikes, occurs during proton injection.
- HERMES requests high electron currents, increasing the number of bunches
to 180. More efforts, i.e. dedicated studies, should be spent on
polarization.
- The preparations for installation of the recoil detector are in
progress.
Milestones for the next 2 months were presented. The detector should
be ready for installation 1.04.05. The preferred start of the shutdown
remains middle of August. The date should be fixed not later then June.
- Matthias Hartig is the new Run Coordinator.
- The TPOL and LPOL are running stably. The measurements are in
agreement. A new TPOL display is available, showing the trend of the
polarization.
- There was a communication problem between TPOL and HERA. The netmex
server was fixed. The ORACLE data base can be updated.
- The LPOL calorimeter was installed last week. It was
re-commissioned without problems.
- The temperature stabilization of the LPOL cavity was installed and
commissioned. The system is working properly, some further tuning
is needed.
- The design of the new LPOL calorimeter is making progress.
The geometry was optimized. A potential
problem of the design is the low light yield. The goal is to
finish the design as soon as possible and start with the production.
Presently, there is no schedule for the fabrication of the new
calorimeter and the commissioning of the cavity.
- A discussion on optimizing polarization will take place end of
January. The requirements and constraints from the experiments
should be presented.
Schedule
- For the time being continue luminosity operation with 120 bunches.
Steady increase of electron current.
- Increasing to 180 bunches will be decided in the weekly HERA meeting.
- The tentative date for the start of the shutdown is second half
of August, length about 7 weeks.
- HERMES is the coordinating experiment.
Date of next meeting
The date of the next coordination meeting is Tuesday, 15.03.2005 10:00hrs,
building 30b room 459.
Uwe Schneekloth