- July 14
- Inserted cathode #33 but tuned (14:00).
- Gun tuned with cathode #33 (16:30).
- July 16
- Dark current 90
A @ 2.2 MW.
- July 17
- Dark current 86
A @ 2.2 MW (06:45).
- Dark current 70
A @ 2.2 MW (20:00).
- July 18
- Dark current 77
A @ 2.2 MW (22:00).
- July 19
- Dark current 71
A @ 2.2 MW (05:17).
- July 20
- Dark current 80
A @ 2.2 MW (21:00).
- July 23
- Dark current 600
A @ 2.2 MW (03:00).
- Dark current 300
A @ 2.2 MW (07:30).
- Dark current 530
A @ 2.2 MW (14:15).
- Dark current 610
A @ 2.2 MW (22:30).
- July 24
- Dark current 550
A @ 2.2 MW (00:50).
- Dark current 1.17 mA @ 2.2 MW (10:30).
- Rotated cathode a little. Dark current 0.58 mA @ 2.2 MW (10:40).
- Rotated cathode again a little. Dark current 0.39 mA @ 2.2 MW (10:50).
- Rotated cathode again a little. Dark current 0.48 mA @ 2.2 MW (11:00).
- Cathode #33 out and #36 in (12:00).
- Cathode transport chamber exchanged.
- Dark current 80
A @ 2.2 MW (22:50).
- July 25
- Dark current 50
A @ 2.2 MW (05:20).
- Dark current 31
A @ 1.8 MW (14:08).
- Dark current measurement. Dark current 108
A @ 2.2 MW (14:18).
- Dark current 80
A @ 2.2 MW (23:08).
- July 28
- Dark current 50
A @ 2.2 MW (19:11).
- July 29
- Dark current 44
A @ 2.2 MW (10:11).
- July 30
- Dark current 100
A @ 2.2 MW (10:11).
- July 31
- Dark current 60
A @ 2.2 MW (19:22).