Minutes of HERA Meeting
04.01.2004
HERA
Peter Hopf is getting involved in the technical coordination of HERA.
F.Willeke summarized HERA operation of last week.
- Starting up the accelerator after the Christmas break went as planned.
First luminosity was
achieved last Tuesday. The first long fill happened Jan 1.
- The specific luminosity is still quite high, up to 2 10**30 cm-2 s-1 mA-2
in one interaction region. It is typically around 1.7 at the other
IP.
- A manual procedure is used to bring the beams into collisions. This
takes about 15 minutes instead of a few minutes with the automatic
procedure. The automatic procedure will be used again once operations
is more stable.
- In general background conditions are fine, except some periods with
increased proton background. Running conditions have to
stabilize. The background oscillations which occurred before
Christmas have not reappeared. A quadrupole magnet power supply
in the north was repaired. It is not clear whether this was the
source of the background oscillations.
- The efficiency has been relatively poor due to several technical
problems: quench protection system, PETRA proton machine, proton
power supply and proton RF system trips last weekend.
Fixing the quench protection system took several days. Some electronics
was changed.
- The improvement of the vacuum pressure in the north IR has slowed
down. NEG pumps will therefore be regenerated tomorrow.
- The aperture limitation SL which was noticed before Christmas has not
been checked again. So far there is no serious problem. A leak check
was performed in December. Temperature sensors were installed.
- Polarization tuning has started. Presently, polarization is around 25%.
ZEUS
- In general conditions are fine. The proton background was still high
for some extended periods ( transparency).
There was also some synchrotron radiation background, which
requires orbit tuning.
- There was a significant radiation dose 31.12.2004 4 and 1krad.
The reason was power supply trips of the electron machine.
HERMES
- Background conditions were really bad at the beginning of fills.
High background appeared during proton injection, significantly
worse than before Christmas. HERA will optimize the proton orbit.
It is planned to re-survey the upstream proton vacuum chamber
during the maintenance day tomorrow. In addition, it will be
checked for radiation. (Nothing was found before the Christmas
break.)
H1
- Some activation occurred during proton injection on 29.12., see
transparency. The background
stayed at a high level after the beam loss.
- During luminosity operation the BTOF background rate is around 100 kHz
transparency. Safe chamber operation
is possible at about 50 kHz.
- The base pressure is at the 10**-10 mbar level. With beam it is
several 10**-9 mbar, above 10**-8 mbar during electron injection ( transparency). The NEG pumps should
be regenerated tomorrow.
- The chamber gas was started yesterday. HV can be turned on from
tomorrow.
Schedule
- Maintenance day tomorrow
- Start warming up GO/GG at midnight
Some proton studies will
be performed during the night shift.
- Interlocks WR and NL will be opened.
- Close tunnel 14:00, close experiments 22:00hrs
- After maintenance day continue luminosity operation with 120 bunches
(no machine studies).
- Priority is stable luminosity operation.
There is still room to increase the
the electron bunch current. A factor of 1.5 increase in luminosity
should be possible without increasing the number of bunches.
- HERMES high density runs will start at Ie=10mA and will last for 1h.
H1 is the coordinating experiment.
Uwe Schneekloth