TTF-2 Full Beam-Loading (9mA) Experiment

Last update: 09.12.2008 (new postings in blue)

Mailing list archive:

            https://lists.desy.de/sympa/arc/ttf9ma

 

Next Meetings (DESY/WebEx)

·       Monday 15.12.2008 15:00 CET: TBC (24/200, WebEx)

General reference material

·       09:12:08 John and Nick’s ~1 hour presentation to the FLASH Seminar (PPT)

·       07.11.08 Material from recent meetings / September run data analysis

·        Proposal for FLASH January 09 studies (PDF)

·        Submitted report on September studies (Carwardine, PDF)

·        04.11.08: Chris Adolphsen’s presentation (September data analysis PPT)

·        28.10.08: Shilun Pei’s updated no-beam analysis presentation (PDF)

·        14.10.08: Shin Michizono’s presentation op beam energy analysis from September data (PPT)

·        14.10.08: Shilun Pei’s presentation on no-beam LLRF data (PDF)

·        14.10.08: Stefan Simrock’s presentation on upgrade options for ACC23 and ACC456 (PDF)

·        07.10.08: Nick Walker’s introduction to meeting (PPT)

·        07.10.08: Siggi Schreiber’s presentation on the status of FLASH dump vacuum (PPT)

·        07.10.08: John Carwardine’s summary of accomplishments at September run (PPT)

·       17.09.08 Week 39 Shift Schedule (PDF)

·       17.09.08 Material from September 16 meeting:

·        Summary of LLRF machine study shifts (J. Carwardine, PPT)

·       01.09.08 Material from August 26 meeting

·        Experience with running long  bunch trains (L. Fröhlich PPT)

·       01.09.08 Material from August 12 meeting

·        LLRF Planning for September (Introduction) (N. Walker PPT)

·        LLRF studies for September (J. Carwardine PDF)

·       06.08.08 Tentative shift plan for September accelerator studies (PDF) (detailed planned to be published next week)

·       06.08.08 Material from general meeting 29.07.08

·        Summary of meeting (J. Carwardine, RTF)

·        September planning status (J. Carwardine, PDF)

·        Summary of LLRF meeting (Grecki/Simrock PDF)

·       15.07.08 Material from LLRF-focused WebEx meeting

·        Summary of meeting (J. Carwardine, PDF)

·        September planning (N. Walker, PPT)

·        9mA Studies at FLASH (M. Grecki, PDF)

·        Potential LLRF collaboration activities… (S. Simrock, PPT)

·       18.07.08 Proposal for Work/Studies for September Shifts (J. Carwardine, RTF)

·       07.07.08 Slides presented to the BAC meeting held on 07.07.08 (part of Katja’s presentation on plans) (PPT)

·       01.07.08 general meeting presentations

·        Experiment status and update (N. Walker, PPT)

·        FLASH 9mA Studies Program: Proposed LLRF related studies (J. Carwardine, PDF)

·        SIMCON-DSP proposal for ACC456 (S. Simrock, PDF)

·       23.06.08: Report from May accelerator studies period (PDF)

·       18.04.08: Material from 18.04.08 meeting

·        top-level goals and planning for machine study periods – Himel (PPT)

·        Status discussions and questions - Walker (PPT)

·        Meeting summary (WORD)

·       14.04.2008 LLRF requirements (use-case) document from S. Simrock (MS WORD)

·       10.04.2008 Draft proposal electronically submitted for TTF accelerator study period 19.05-01.06 (PDF)

·       18.03.2008 High-power requirements for dump (email from M. Schmitz)

·       27.02.2008 Walker/Himel presentation at preparation meeting (PPT)

Relevant reports/presentations to ILC-GDE

·       21.05.08 LLRF for FLASH 9mA Studies [PDF]

·       11.06.08 FLASH 9mA beam studies: HLRF/LLRF integration (J. Carwardine) [PDF]

·       17.06.08 Status report on RF for FLASH 9mA Studies Program (J. Carwardine) [PDF]

·       19.06.08 FLASH 9mA Studies Program: RF Integration (J. Carwardine) [PDF]

Experimental program (LLRF) proposals and related documents

·       23.06.08 Proposal for LLRF studies (S. Michizono) [WORD]

 

Meetings (DESY/WebEx)

·       next: Tuesday 15.07.2008 at 15:00 (tentative: LLRF specific)

Important dates

07.07.2008

FLASH BAC meeting

Present proposal to BAC

slides

19.05-01.06.2008

Accelerator Studies via bypass

Initial sub-systems test for experiment

report

23-27.09.2008

Accelerator Studies via bypass

Further sub-system tests with long bunch trains

report

12.12.2008

FLASH seminar

05-18.01.2009

Accelerator Studies via bypass

Further sub-systems test as needed

proposal

18-20.01.2009*

Mini-workshop on 9mA experiments

TBC: dates to be in conjunction with January machine shifts

 

06-24.05.2009

Dedicated 9mA experiments

 

 

           

Contacts (action items)

 

Current Distribution List (updated 7.11.2008)