The CJC2 chamber scales linearly with the positron beam current. The estimate
of the maximum current (positron beam only) is 50mA. The observed number
of random hits is roughly in agreement with the calculations. For proton
beam only, the drift chamber can probably be turned on up to currents of 100mA (There
is a large uncertainty on the maximum current. The extrapolation
is based on 3 points.) For luminosity operation, the maximum beam currents
are given by the product: Ie*Ip=600mA**2.
The dynamic vacuum still needs to improve by a factor of 3. During collisions
3/4 of the events have a z-vertex at the C5b collimator. A reduction of
the collimator thickness is being studied.
A tilt and position scan of both beams should be done. A test run at reduced
proton beam energy was proposed in order to study the proton background.
HERMES
-
So far HERMES has only had 4 days of useful data taking this year.
-
The detector is ready for data taking. At positron currents of 15mA,
corresponding to a factor of 3 less luminosity than in 2000, big parts of
the physics
program (like DVCS) are not possible as there is no beam polarization
and a continuous running to take data for transversity needs an increase
in HERA-e currents from 15mA to 30 mA until October.
-
Polarization studies are considered to be essential.
HERA B
-
Commissioning of the detector has been very inefficient. HERA B got only
4 hours of beam time during the last 10 days. In total, about 42 shifts
are required for detector commissioning until September. Half of this has
been done so far. 60 proton bunches are fine for commissioning (interaction
rates of 1 - 2 MHz). The full bunch structure is needed for data taking.
-
HERA-B pointed out, that in case a long shut down to modify the
interaction regions of H1 and ZEUS will happen, HERA-B will make very
strong request to get enough dedicated beam time BEFORE this shut
down to complete his physics program, since there is a high
probability that HERA-B will not be in a position to switch on the
experiment again after such a shut down.
Summary and Priorities
R.Klanner
summarized the discussion and defined the priorities. Although there has
been significant improvement on understanding of the background conditions
at H1 and ZEUS, R.Klanner expects faster progress when the simulation
tools are available. During luminosity operation HERMES and HERA
B should have priority in order to proceed with their physics programs.
Until
the next HERA coordination meeting the weekly schedule is:
-
Monday to Wednesday: machine shifts and dedicated background studies.
-
Thursday to Sunday: luminosity operation using the beam and bunch parameters
proposed by F.Willeke. After some runs for re-establishing luminosity at low
currents, the positron current will be slowly increased starting at 20mA
in 60 bunches. HERA will then go to 120 bunches.
The
date of the HERA coordination meeting will be moved from 02.09.2002 to
end of September. The shutdown schedule should then be finalized. A preliminary
version of the schedule should be circulated 2 weeks before the meeting.
Uwe Schneekloth