Minutes of HERA Meeting 25.10.2005
HERA
F.Willeke summarized HERA operation of last week
( transparency)
- HERA delivered 9.2pb-1 in 12 runs, a new record for the weekly
luminosity. The maximum luminosity was 5.1 10^31 cm-2 s-1.
The efficiency was 68%.
- There were some periods with high backgrounds, which required careful
tuning.
- Another leak occurred in the rotator section NR a few meters away from
the leak of last week. A bellows section had to be replaced.
- The current of the rotator magnets was scanned in the north and south.
The results are as expected. There are no hints which could explain
the asymmetry.
Shutdown activities
- The shutdown activities are unchanged, except for addition work on the
vacuum system and an orbit stabilization feedback.
- The (28) bellows in the rotator sections will be modified in order to
prevent any further leaks.
- A cavity window will be exchanged SR. New ion getter pumps will be
installed in this RF section.
- An orbit stabilization feedback for the electron beam is in
preparation. Some simple correction coils have to be installed.
ZEUS
Y.Yamazaki summarized the ZEUS status ( transparencies)
- Unfortunately, the week was not so good. There were many chamber trips.
Beam tuning at the beginning of the fill took a long time. In
addition, there were trips with unknown reasons, some possibly due to
synchrotron radiation background.
- In general, the proton lifetime was good (>200hrs), not causing any
trigger problems.
- F.Willeke remarked that
the background conditions become more critical with higher electron
currents.
Large drifts are observed, which require re-tuning of the machine.
Sometimes the proton collimators do not reach the file values if the
collimator rates are high.
Yesterday the proton emittance was already somewhat poor at the
beginning. The synchrotron radiation background was checked.
Shutdown, W.Zeuner ( transparencies)
- The schedule has not changed. The installation tool for the FDET is
ready. The deformation of the GO temporary support is as expected,
when a horizontal force is applied.
H1
P.Laycock summarized the H1 status transparencies:
( HV efficiency)
( int lumi)
( HV efficiency vs day phase 2)
( HV efficiency vs day)
- Data taking was very good last week. The average HV efficiency was
83%.
- The integrated luminosity with HV on has now reached 100pb-1. The
recent slope luminosity vs. day is very nice.
Shutdown, G.Eckerlin ( transparency)
- There are no changes in the shutdown schedule.
- Flammable gases will be stopped Friday (11.11.) morning.
- After re-installation of the vertex detector, pumping down will be
started before the Christmas break.
HERMES
- The background conditions did not improve since last week. The electron
background was usually high at the beginning of the fill, the proton
background increased during the run.
This did not prevent HERMES from data taking, but required pre-scaling
of some triggers.
Shutdown, J.Stewart ( transparency)
- There are no major changes of the schedule.
- The polarized target will be removed. The size of the new beam pipe
and collimators will not be changed.
Polarimeters
- The group is trying to get the cavity polarimeter running before the
end of the data taking period. An access is needed to exchange some
electronics. This will be done during the next calibration of the
ZEUS calorimeter.
- No major activities are planned for the shutdown.
Schedule
- Continue luminosity operation. Try to increase electron current.
- Luminosity operation will stop Friday (11.11.) morning. HERA will
continue with 3 days of machine studies.
- Tests of the orbit stabilization feedback.
- Check whether the aperture is sufficient for new optics. The idea
is to reduce the size of the proton beam at the IP for a better
match of the beams. The electron beam is presently smaller due
to the pinch effect.
- The solenoids and luminosity monitors should be on for the machine
machine studies.
H1 is the coordinating experiment.
Uwe Schneekloth