Minutes of HERA Meeting 18.10.2005
HERA
M.Bieler and B.Holzer summarized HERA operation of last week
- HERA delivered 8.1pb-1 in 12 runs, in spite of a vacuum leak. The
maximum luminosity was 4.5 10^31 cm-2 s-1. The efficiency was 60%.
The total delivered luminosity is now 189pb-1.
- In general, background conditions were acceptable. The proton orbit
was critical. The proton background was improved by changing the
proton orbit upstream of the IPs. This is somewhat difficult
due to problems with the beam position monitors in the straight
sections. (Some of the BPM electronics will be replaced during the
shutdown.)
- Last Wednesday a leak occurred in the rotator section NR. The
support welding seam, which had been added during the last shutdown,
was not strong enough. The vacuum recovered relatively quickly.
All 28 similar bellows sections in the rotators will be fixed in the
shutdown.
- The electron transmitter WL was repaired this morning.
- Polarization was significantly less than the previous week. The electron
tunes could not be reduced as preferred for good polarization due
to electron background conditions.
A rotator scan (scanning BF magnet) was prepared and will be started
during the next fill.
- The NEG pumps in the rotator section NR will be activated in case of
a break.
ZEUS
Y.Yamazaki summarized the ZEUS status ( transparencies)
- The detector performance was relatively good. The average data taking
efficiency was above 80%. The baseline background is low. There were
however some periods with background spikes causing HV trips.
H1
P.v.Mechelen summarized the H1 status ( transparencies)
- 6.5pb-1 were written to tape. The HV efficiency was 82%, compared to
64% last week.
- The total integrated luminosity (H1 active) is now 180pb-1, 97pb-1 with
HV turned on.
- The present fill started with somewhat high proton background. It
was improved by changing the proton orbit upstream of the IP.
This fill is suffering from satellite bunches.
HERMES
- The detector is performing fine. The main concern is high proton
background. Calibration triggers had to be pre-scaled.
- Large electron background has been observed, in particular at the
beginning of a fill, since the leak in the rotator section.
- There were only few high density runs this week due to unscheduled
beam dumps.
Schedule
- Continue luminosity operation. Try to increase electron current.
- A rotator scan (BF magnet) will be started next fill.
- The NEG pumps (rotator section NR) will be activated in case of a longer
break.
- The shutdown activities will be reviewed in the meeting next week.
ZEUS is the coordinating experiment.
Uwe Schneekloth