Minutes of HERA Meeting 13.09.2005
HERA
F.Willeke summarized HERA operation of last week
- The maintenance day last Wednesday went as planned. The machine studies
were delayed due to problems with the interlock. Luminosity operation
resumed Friday to Saturday night.
The first two fills lasted only a
few hours. The specific luminosity was relatively low.
The third fill was was very quiet, high luminosity and good
background conditions.
- Luminosity operation stopped Saturday to Sunday night because of two
leaks in the electron vacuum system
(rotator section east right and absorber SR11).
- The leak east right occurred due to overheating of an absorber
which protects the vacuum chamber from synchrotron radiation.
Up to 5kW of synchrotron radiation is deposited on 3 cm^2. The
synchrotron radiation had been overlooked in the original design,
causing a leak in 1997. Absorbers were added in the next shutdown.
It is not clear why the vacuum chamber got hot. The only
explanation is insufficient thermal contact between the absorber
and the beam pipe. The water cooling was checked. All other
locations were checked as well.
The vacuum chamber was removed yesterday morning. A spare chamber
is presently being prepared. It will be installed tomorrow
afternoon.
- The leak at the electron flange SR occurred after the electron beam
loss. The same flange had several leaks before. Last time,
in early March, it was fixed by tightening the screws.
It was therefore decided to replace the seal. Yesterday
the GO/GG magnets were warmed up, the IP was vented. Today the
seal was replaced.
The same procedure will be used for activating NEG pumps as in
April 2004, when the vacuum recovered very quickly.
- The startup schedule will be discussed tomorrow morning.
- The position of the spin rotators was changed during the maintenance
day. Polarization was 20% without any tuning. The first bump scan
was started.
- The proton beam losses at HERMES during injection were reduced.
ZEUS
- CTD operation was problematic on the weekend. The HV continued to
trip after the synchrotron radiation background had been improved
although the background was quite low. Trips were also observed
without beam.
The HV system is presently checked by experts.
H1
D.Pitzl summarized the H1 status
(CJC current,
fast track trigger rate,
vacuum)
- The CJC current is now, after regeneration of NEG pumps, below the
expectation. The normalized fast track trigger rate improved
significantly. It is now 0.7. The vacuum at the IP is similar
to the pressure in the south.
HERMES
- Shifts are canceled until Wednesday morning.
Schedule
- Beam operation will not restart before tomorrow evening. The startup
schedule will be discussed tomorrow morning.
H1 is the coordinating experiment.
Uwe Schneekloth