Minutes of HERA Meeting 9.08.2005
HERA
F.Willeke summarized HERA operation of last week
(transparency)
- Luminosity operation was fairly good last week. HERA delivered 6.25 pb-1.
Beam currents were Ip 80 - 90mA, Ie 28 - 35mA.
- After the break on Thursday machine operation restarted as planned.
Proton background conditions were somewhat painful, in particular due
to GA spikes. The original power supply had been reconnected on
Thursday.
The background conditions improved after switching back to the spare
power supply Sunday afternoon.
- Several technical problems occurred: proton quench protection dump
switch, sextupole measurement, coupler window temperature of
superconducting cavities, phasing of cavities and proton RF system.
- The electron collimator procedure was changed yesterday in order
to reduce the background during acceleration.
- The superconducting cavity, which was removed a few weeks ago, should
be ready in about 2 weeks. Re-installation will take 2 to 3 days.
It is not yet clear whether this will be done during the maintenance
day in September or whether the maintenance day will be moved forward.
ZEUS
Y.Yamazaki summarized the ZEUS status
(transparency)
- The barrel calorimeter was successfully repaired during the access on
Thursday. (Thanks to HERA and other experiments for the access.)
- Proton spikes came back on Saturday causing frequent HV trips.
The luminosity loss due to spikes was between 10 and 40%.
- Except for the very first part of the fills, the proton background was
usually about a factor of 2 higher than the baseline background.
The collimator positions should be retuned.
H1
D.Pitzl summarized the H1 status
(delivered luminosity,
beam currents ,
specific luminosity ,
HV efficiency ,
projected luminosity)
- So far HERA has delivered about 125 pb-1 this year. The luminosity on
tape with HV on is approaching 70 pb-1. 30 pb-1 have been taken with
the present rotator setting. Changing the beam helicity should be
discussed next week.
The overall slope of delivered luminosity is similar to the slope in
February. The progress is disappointing.
- Beam currents are still relatively low.
The specific luminosity was quite good, slightly above 2 10**31 cm-2 s-1
mA-2 at the beginning of a fill.
- The HV efficiency was up to 90% for good background conditions.
Sunday morning before the switch back to the spare GA
power supply it was only 40%.
- Vacuum conditions have been stable since the beginning of July, the
last time the NEG pumps were regenerated. Firing TSP's twice per
week keeps the vacuum at a constant level. Improvements have only
been observed after NEG regenerations. This should be repeated
during the September and October maintenance days.
- Last Tuesday the GO magnet was moved 1.5mm ring outwards. The dipole
current was reduced.
- At NL220 the proton orbit was moved horizontally by 8mm to increase
the acceptance of the VFPS. A 7mm orbit bump is now in the file.
The pots were moved in 6mm.
- The photon spot in the luminosity monitor is still 1.5cm off, introducing
an acceptance correction of 10%. The offset should be corrected.
The tilt bump is presently used to correct the dispersion.
Alternative bumps are being studied by the machine group.
HERMES
- Good data taking. The background during proton injection improved by
a factor of 10 to about 1 MHz. It should be improved further.
- A 1 h access is needed to repair a defective chamber.
- Since last week the LPOL/TPOL ratio is off by 20%. It is not yet clear
why.
- Polarization is slightly worse than before, not approaching 50% at the
end of a fill.
Schedule
- As always, aim for increasing luminosity, low background conditions and
high polarization.
- The change of helicity will be discussed in the meeting next week.
HERMES is the coordinating experiment.
Uwe Schneekloth