Minutes of HERA Meeting 19.04.2005
HERA
F.Willeke summarized HERA operation of last week
- The exchange of the BU coils SR was finished on Thursday evening,
faster than expected. There was some delay due to a leak in the
proton vacuum system (the seal had to be replaced and repair of cables
of temperature sensors). Proton beam operation started again Friday
afternoon.
- HERA delivered 6 luminosity fills since Saturday. The electron current
was reduced to 35mA.
New files had to be made since the orbits had drifted.
The proton background spikes disappeared. Some tuning is still
necessary to optimize the conditions.
- Last night the proton aperture was limited NL (very small injection
efficiency). The reason was the H1 VFPS, which was still in the beam
position. The VFPS position should be included in the interlock.
- The collimator jaws to beam procedure will be used a few times
before a new collimator file is made.
- Electron mirror tunes were tested during the night shift Thursday/
Friday. The beam was accelerated without problems.
- Another iteration of harmonic bump scan is necessary to improve
polarization.
ZEUS
R.Carlin summarized the ZEUS status
( transparencies)
- During the weekend the proton background was about a factor of 2
higher than the expectation. One contribution was due to the poor
vacuum in the section which was vented. The pressure and
baseline background
conditions improved yesterday after firing of TSPs.
There are however still
proton background problems which are not related to the vacuum.
Conditions are fine for the present fill.
H1
J.Ferencei summarized the H1 status
( transparencies,
HV efficiency)
- HERA delivered 6 fills. The integrated luminosity was 2.77pb-1, 2.28pb-1
on tape. The HV efficiency was typically between 60 and 70%. The
first fill on Saturday was bad (HV efficiency 37%),
the fill yesterday morning excellent (94%). The electron background
was usually decreasing as a function of electron current. The
proton current was sometimes increasing. The fast track trigger
was still fluctuating a lot.
- A new water Cerenkov counter was installed after the filter, just before
the luminosity calorimeter. The Cerenkov rates are available on the
luminosity display.
- The electronics of the VFPS was not damage when the pots were left in the
beam position last night. The VFPS position will be included in the
interlock.
HERMES
M.Hartig summarized the HERMES status
( transparencies)
- The target cell was exchanged last week. With the new cell the
target polarization improved from 0.7 - 0.8 to 0.8 - 0.85.
The so-called depolarization factor is however slightly lower (0.84
instead of 0.87).
- Data taking resumed without problems. Proton background was bad twice
during injection. HERMES would like to be informed before the proton
beam is scraped. The top/bottom rates should be similar.
- Higher electron polarization is appreciated.
Schedule
- Luminosity operation. Fine tuning of background conditions,
optimize collimator positions.
Increase beam intensities.
Shutdown Plans
- The machine group is proposing to start the shutdown in November
in order to replace all remaining BU coils.
Only half of the coils could be replace if the shutdown starts in
August.
- The proposed dates are:
- Start of shutdown 14.11.2005
- End of shutdown 18.01.2006
- Start beam operation 6.02.2006
- The plan is to have no further shutdown until the end of HERA
operation provided the authorities agree on increasing the time
between the interlock tests.
Note added after the meeting: The Amt fuer Arbeitsschutz agreed
on having no further interlock test after Jan 2006.
- A decision on the shutdown date will be made in the HERA coordination
meeting in two week.
HERMES is the coordinating experiment.
Uwe Schneekloth