Minutes of HERA Meeting
20.01.2004
HERA
- The superconducting cavity, which had a leak, was disconnected from the
RF during the access Tuesday and Wednesday. It is one out of 16
superconducting cavities.
The radiation safety check of the transmitter
SL was done. The transmitter is again in operation. Higher positron
currents are now possible. The goal is to increase the positron current
to 35mA before going to the full number of bunches.
- HERA delivered 10 luminosity fills since Thursday with maximum proton
currents of 64mA. There were no major technical problems.
- Proton background conditions were poor for some fills, in particular
for ZEUS. The source of the background is not known.
It was improved by changing the proton tunes.
- The preliminary results of the longitudinal beam scan presented last week
were revised. The data are well described assuming the design beta functions
(p vertical beta function of 0.198m instead of 0.18m) and a scaling factor
of 0.79. It is not understood why the scaling factor is needed. There
are no indications for dynamic effects. The transverse scan has not yet
been done. There will be a special meeting on Monday 16:00hrs to
discuss the specific luminosity and required studies.
F.Willeke summarized the progress on the measures against accidental proton
beam losses.
- The work is progressing as planned with a few exceptions.
Regular meetings are being held.
- Increased preventive maintenance of the low-beta proton magnet
power supplies is being done since November.
- Connecting power supply alarms to the alarm loop: A test was
successfully done in December. A prototype of the final electronics
is being assembled and will be tested next week. 16 of the 40 power
supplies will be equipped during the February maintenance, the
remaining power supplies in March.
- Monitoring of fast current changes of power supplies: The design
of the electronics is ready. A prototype will be tested end of
January. Critical power supplies will be equipped in March (slight
delay).
- Beam dump signal without delay: Was implemented in December. Is in
operation without problems.
- Faster processing of alarm loop signals: Electronics was changed
during January maintenance day.
- Fast AC beam current monitor: In operation. Issued a beam abort
signal when a GA failed on 21.12.2003.
- Fast DC beam current monitor: Electronics installed in December.
Being tested. Created two false alarms. Waiting for final approval.
- BPM alarms: Working in principle, not active. Reference orbits and
thresholds have to be improved. Goal: active in March.
- Proton collimators are moved closer to the beam during e-injection
and acceleration since December.
- Additional beam loss monitors (scintillators) at north IP: Work
in progress.
H1
- HERA delivered 1.5pb-1 last week, H1 took 1.2pb-1 (0.84pb-1 with all HV
on). In general, background conditions were acceptable.
- The scaled chamber current is not improving as a function of time.
The maximum beam currents are still Ie x Ip= 30mAx60mA.
Warm-up of GO/GG and
regeneration of NEG pumps has to be done during the February maintenance
day. The central beam pipe got hot and the vacuum quite poor when the
positron injection took a long time.
- Proton collimators and p orbit should not be moved without agreement from
all experiments.
ZEUS
- Background conditions were acceptable for some fills. For other fills the
proton background was very unstable (visible in C5 and proton collimator
rates), causing frequent HV trips.
- A calibration run for the luminosity spectrometer was taken yesterday.
This did not affect the calibration of the photon detector.
HERMES
- HERMES had only 3 good fills after the access. At the beginning of the
fills the background was quite high. HV could only be turned on after
about 2 hours. Yesterday the proton background was high.
- The target was repaired during a temporary access.
Polarimeter
- The DAQ system of the cavity LPOL has been improved. Compton
photon have been observed. A 2 hours access is required to replace
a defective camera.
Schedule
- Continue luminosity operation with increasing beam currents.
- Access for LPOL cavity in case of a break or in coincidence with
calibration of ZEUS calorimeter.
- Meeting on specific luminosity and required studies on Monday 16:00hrs.
H1 is the coordinating experiment.
The time of the HERA meetings was changed to 10:00hrs in order
to avoid conflicts with the WA.
Uwe Schneekloth