H E R A C O O R D I N A T I O N M E E T I N G ================================================== 27.10.1998 10:00 Short summary: -------------- 1) Shutdowns '99 a) Xmas : 21.12. 6:00 - 6.1. 22:00 b) spring: 3.5. - 12.6. (6 weeks) c) 2nd half of year: extension of monthly maintenance days to 64h mini shutdowns for HERA-B installation proposed (to replace 5 week fall shutdown) 2) Luminosity upgrade shutdown: 2 scenarios a) November '99, 9 months b) Spring '00, 9 months All parties involved should make a realistic schedule and not count on an second long shutdown a few years later! Decision on next coordination meeting with additional input from HERA-B. 3) Running strategy During the ongoing background studies the HERA-B target wire operation will stay unchanged (insertion after lumi tuning), later longer 'target times' should be possible.