Minutes of HERA/Experiments Coordination
Meeting 30.08.2005
Agenda
- Brief status reports, HERA and experiments
- Operation until shutdown
- Shutdown
- Status and milestones of shutdown preparation
- Shutdown schedule
- Date of next meeting
- AoB
Minutes:
Accelerator performance July/August
- The beam currents have not increased. The proton current is slightly
reduced due to problems with PETRA.
There has been no progress increasing the electron current due to
recovery from technical problems, dust and other lifetime problems,
background conditions and injection tuning problems. It seems hard
to get beyond 40mA.
- The peak luminosities, 3 - 4 10^31 cm-2 s-1, are slightly less than
in May (maximum 5.1 10^31). The specific luminosity continues to be
large, unless the machine is not properly tuned. Luminosity production
in August was fine, about 25pb-1 were delivered, but the data taking
efficiency was poor due to worse background conditions.
There are no indications that the recent poor background conditions
were due to technical problems.
Polarization
- Polarization is in good shape, i.e. about 30% at the start of a
luminosity run, approaching 45% towards the end. The non-colliding
bunches have up to 60% polarization.
- The rotator settings for the different positions were checked.
The sensitivity to the settings is larger than expected.
Short term plans
- The maintenance day Wednesday next week will be from 6:00 to 22:00hrs.
The tunnel will be closed at 14:00hrs.
- It was decided to warmup the GO/GG magnets in the north IR in order
to regenerate the NEG pumps. GO/GG will stay cold in the south.
- HERA will resume operation with one day of machine shifts to explore
the beam stability.
- The rotator position will be changed. Polarization has to be retuned
again.
Shutdown planning
- The shutdown dates are 14.11.2005 to 6.02.2006 (restart of beam
operation). Luminosity operation is scheduled to start in the third week of
February.
- The major shutdown activities are: replacement of BU coils,
re-installation of the cryostat #1
with superconducting cavities, a new proton multi-bunch feedback
system, and maintenance work.
The BU coil delivery is slightly ahead of schedule. 21 coils are here.
The last 4 coils will arrive in October.
The superconducting cavities will be cold-tested in the PETRA hall
NE prior to installation, which is scheduled for 12.12.05.
- Both polarimeters have been operating very smoothly. The efficiencies
are: TPOL 98.2%, LPOL 96.9%, both 99.8%. The measured peak polarization
was up to 50%. There were no significant hardware problems.
The period of low LPOL luminosity (2 weeks in July) was fixed.
- The main problem is a significant shift of the LPOL/TPOL ratio (0.9 to
0.95) in the
last few weeks. Both measurements have been checked. There is no
obvious problem.
- The LPOL cavity performs well, but is still far from routine operation.
First Comptons were observed some time ago. Presently, work is in
progress to understand the laser polarization.
The new calorimeter was built, checked in the DESY test beam and
installed in June. Commissioning is in progress.
First data were taken in the HERA tunnel (not
yet Compton events). The timing still has to be optimized.
A list of task exists, but no detailed schedule. The group is trying
to get additional manpower.
Operation
- H1 has now collected 76pb-1 with HV on. The average efficiency is 59%.
The e- p data sample is now 5 times as large as the HERA I electron
sample.
- The specific luminosity is usual quite high. It has increased again
in recent fills, sometimes as high as 2.2 10^30 cm-2 s-1 mA-2.
- The average polarization did not decreased after HERA switched back
from mirror to standard tunes.
- Last week the integrated luminosity was relative low with poor
background. The conditions were much better on the weekend.
- The HV efficiency is between 70 and 90%. Last week it was lower due
to the poor electron lifetime. The normalized proton background
(fast track trigger rate) has increased slightly. The NEG pumps
should be regenerated during the maintenance day next week.
- Stability of machine operation is a major concern. A significant
increase of luminosity is essential for the H1 physics program.
Silicon repair
- The silicon detectors and hybrids will be reused for the BST,
equipped with radiation hard chips. All modules are ready. Mounting
is in progress.
- Everything is new for the FST, except the mechanics. Module assembly
is almost completed (90% done).
- The work is on schedule and will be ready for installation during the
shutdown.
Detector operation
- The detector is running fine. The gated luminosity is 102pb-1 out of
139pb-1 delivered.
- Recently, the efficiency was low due to background problems. Low
proton (less than 50hrs) and electron lifetimes (less than 5hrs)
cause severe
problems. The situation has significantly improved since Saturday.
On Sunday ZEUS recorded 1.3 pb-1.
- Occasionally high trigger rates dead-time are observed with reasonable
proton lifetime. Background tuning is essential, in particular the
collimator positions.
- The change of helicity next week is supported.
Shutdown planning
- The preparations for the shutdown are on schedule. There was some
delay of the main carrier of the STT installation jig due to
other work in the mechanical workshop. This is not a problem.
- The cooling system for the frustum is under construction.
- Preparation for some other repairs are in progress.
Data taking
- HERMES has collected about polarized 3.8 Mio DIS events 2005.
The efficiency
is similar to 1997, but still worse than in 2000.
The detector is in good shape.
- About 9 Mio unpolarized events have been taken. Last month the
gas was changed from Xe to Kr.
- The cooling problems were solved. An independent cooling system is not
required anymore.
- The beam polarization is still low. The helicity asymmetry is
opposite compared to 2004. The helicity should be changed next
week. Another change of polarity might be requested in October.
Recoil detector and shutdown
- The recoil detector test experiment is running and taking
cosmics. The data is used to determine the efficiency
of the different components. The DAQ is ready for integration
into HERMES.
- Dismantling of the test experiment will start 5.09.2005 in
order to prepare for installation.
- The shutdown schedule is tight. The main activity will be the
installation of the recoil detector. In addition, HERMES has
to be moved to the service position for the replacement of
BU coils. Some task like survey are already been done
at the regular maintenance days.
Schedule
- The HERA shutdown will start 14.11.2005
- The rotator positions will be changed during the next maintenance day.
- One day of machine studies will be performed after the access.
- HERMES is the coordinating experiment.
Uwe Schneekloth