Minutes of HERA/Experiments Coordination
Meeting 21.02.2003
Agenda
- Brief status reports
- Recommendations of background review committee
- Operation until shutdown
- Shutdown dates
- Date of next meeting
- AoB
Minutes:
Progress since last meeting
- Higher intensity positron operation in December failed because of
vacuum problems of the superconducting cavities. The cavities were
warmed up to room temperature during the Christmas break to release
gas.
- Warming up the GO/GG magnets in the north and south interaction
regions during the break did not give any significant improvement of
the vacuum.
- The startup was promising. 36mA of positron beam could be injected
after 2 days of operation. There were several luminosity fills
with Ie > 30mA.
- Progress was stopped by a non-understood intensity and energy dependent
positron lifetime problem. Attempts to locate the lifetime problem
by beam steering caused vacuum leaks NR11 and NR14. The vacuum
system of the interaction region was vented to 1mbar. The pressure
is now at 5 10**-8mbar instead of 2 10**-9 before the incident.
Proposed running
- It was proposed to warm up the GO/GG beam pipes to room temperature
and to do one week of high intensity beam bake-out at 12GeV.
During the bake-out proton beam should be kept in the machine.
- Continue with high positron intensity luminosity operation after
the bake-out.
- Machine studies last two weeks of February.
High priority items before the shutdown are:
- Increase positron intensity to 50mA
- Achieve luminosity of 4 10**31 cm-2 s-1
- Demonstrate further progress in proton background
- Ensure that north and south spin rotators work properly.
- The detector is in good conditions. At the present beam currents background
conditions are usually acceptable. The aim is to collect at least 2pb-1 with
CTD and MVD turned on. So far got 30%.
- No improvement of the vacuum and CTD chamber currents was observed
after the Christmas break
- The following questions should be answered before the shutdown:
- Can HERA operate with 50mA in colliding beam mode
;Proposal: continue running with increasing positron currents.
- Contribution of higher order mode losses to proton background?
Proposal: several ep fills, positron beam at 12GeV.
- Are rotators sources of additional background?
Proposal: ep operation with rotators switched on.
- Check off-momentum positron background from GA magnet region.
Proposal: heat TSP pumps.
- Check background contributions. Need high intensity positron beam
only fill.
- Proposed schedule:
- Continue running until 27.01.2003 with increasing positron currents.
If Ie=50mA is reached, continue with 12GeV running for 2-3 days for HOM studies,
one long positron only fill, rotator studies. If 50mA is not achieved until
27.01., postpone high intensity running until end of running period.
- Shutdown activities (total length 18 weeks):
- replace C5 collimators,
- repair Straw Tube Tracker,
- minor repairs of detector, exchange under-carriage of iron yoke
- The detector should tolerate background conditions at a luminosity
of 4 10**31 cm-2 s-1 mA-2 (CTD HV off).
- The CTD trip limits were set very conservatively. No significant loss
in gain has been observed so far. The plan is to increase the thresholds.
H1, D.Pitzl transparencies
- The total delivered integrated luminosity is 8.0 pb-1.
The collected luminosity is 6.3pb-1 (H1 active), 2.0pb-1 (HV on), which
is limited by high background conditions and background spikes.
- The chamber currents improved by a factor of 20 over 100 days. In
December, the vacuum pressure at the IP was a factor of 2 higher than in
2000.
- The IP vacuum system was vented on 12.01.2003 due to a leak at the
main absorber. The proton beam gas background is still too high to turn on
the CJC high voltage . Recovering from the previous leak took 20-30 days.
- Proposed schedule:
- Bake-out at 12 GeV
- Continue luminosity running. Parasitic background studies: heat
TSPs NL and NR.
- Turn spin rotators.
- Increase positron current >40mA at 27.5GeV.
- Shutdown activities (total length 17 weeks):
- Installation of the VFPS. The VFPS bypass cold test started at
DESY yesterday.
- Modification of C5b collimator. The proposal is to have vertically
asymmetric jaws to compensate for the H1 offset with respect to HERA.
- Repair of CIP electronics. Mounting SMD components failed. A new
technique is used. First results are expected next week.
- Improve background monitoring (add Si PIN diodes).
- The trip and operational limits of the CJC are not conservative.
Some degradation of the gain was already observed before the luminosity
upgrade. The HV was reduced in 2000. The single wire efficiency is 95%.
HERMES, D.Ryckbosch
transparencies
- The detector is in good shape. Data taking is not limited
by the background conditions. About 250k DIS events were taken in November.
The delivered luminosity was much lower in December and January.
- The positron current was not increased in January.
- The total data sample is 684k DIS events. The projected data sample
until the end of the running period is 0.85M events. 1.4M events are needed
for a meaningful physics program.
- Requests:
- Non-colliding beam operation between now and 17.02.2003. The effective
gain for HERMES would be 20-40%
- Dump positron beam at 10mA, gain 20-30%
HERA B, M.Medinnis
transparencies
- The tungsten wire was damaged again (3rd time). The damage was
associated with beam movement. Another W wire (so-called emergency wire)
is presently used for data taking. It has poorer rate stability. It is planned
to replace the broken wire during the access in February. This will take
16 hours plus time for pumping.
- HERA B did not get much running time in January. The total J/Psi
data sample is 150k events. The proposal was 2M events. The physics program
is highly statistics limited. A Psi' measurement does not seem to be possible.
- Request:
- 6 week proton only run before the shutdown This would increase
the data sample by a factor of 8-9.
- Some collaborating institutes committed to HERA B only for this running
period. It would be difficult to turn on after the shutdown. The possibility
of stable proton beam running during 12GeV positron beam bake-out after the
shutdown was discussed. It is not clear whether this is realistic.
Recommendations of Background Review Committee
Summary, R.Klanner
- Interlock tests in March
are mandatory, which will take 3 weeks.
- The synchrotron radiation
background is well understood. The understanding of the proton beam gas background
is reasonable, although not complete. No major new ideas have come up so
far. It is not yet clear whether the proposed modifications will be ready
on time.
- A review committee will
be set up to review the engineering aspects of the proposed changes to ensure
that they are technically sound. The directorate will be in close contact
with the committee. Resources in the mechanical shops will be allocated.
- Although there are certain risks, the directorate decided to begin
the shutdown 03.03.2003. It is clear that is a major set-back for the HERA
B and HERMES physics programs. The hope is that HERA B will be able to take
data after the shut-down (stable proton beam during 12GeV positron beam bake-out).
- The readiness of the modified collimators, H1 CIP electronics repair,
GA magnet electron vacuum chamber and coating of the main absorber was discussed.
It is not yet clear whether the HERA tram will be needed for opening of the
GA magnet.
Schedule
- Starting today, one week of 12GeV positron beam bake-out. Proton beam
will be kept in the machine for HERA B. (HERA B has to turn off for about
15 minutes for positron re-injection.) The GO/GG magnet beam pipes will be
warmed up to 170K during the bake-out.
- Tuesday next week continue with luminosity operation.
- The further schedule will be discussed in the weekly HERA meetings.
- Machine studies 17.02.2003 to 03.03.2003
- Shutdown start: 03.03.2003, length 18 weeks.
- ZEUS is the coordinating experiment.
Uwe Schneekloth