Minutes of HERA/Experiments Coordination Meeting Monday, 19.11.2001
_________________________________________________________________________
Agenda
- Present status
(Progress on HERA commissioning, understanding of background conditions,...)
- Luminosity run after November access
(Expected HERA performance, requests by experiments, ...)
- Work during Christmas break
(Fix dates of Christmas break)
- Schedule for HERA operation in 2002
(Fix access days)
- Conditions/Date for switching to electrons
(Unless there are new convincing arguments, we should not reenter into a
physics discussion.)
- First discussion on polarity of spin rotators and time between changes
(HERA prefers to have only 2 different setups, i.e. all rotator positions
should be changed at the same time if possible.)
- First discussion on longterm planning of shutdowns.
- Date of next meeting
- AoB
Presentations:
News from the DESY Scientific Council (WR) R.Klanner
The evaluation of the TESLA TDR was very positive. The WR congratulated
DESY for the good performance.
The WR agrees with the recommendations of the PRC.
The WR agrees with the "Policy concerning the operation of HERA and PETRA.
This should include a fixed date for the modification of PETRA and end
of the HERA II program (31.12.2006). The HERA II physics program should
have highest priority. The WR strongly recommends building an additional
ring in the PETRA tunnel (2nd option in the paper). Proposals for a
HERA III program should be submitted until end of 2003.
Joachim Mnich, Aachen will be new PRC member (H1 referee).
HERA F.Willeke transparencies
ZEUS W.Zeuner transparencies
H1 E. Elsen transparencies
HERMES J.Stewart Detector Status transparencies Beam loss monitors transparencies
HERA B A.Spengler transparencies
Polarimeter T.Behnke transparencies
Schedule
First luminosity running starting 22.11.2001
Turning on rotators in December might be postponed. Understanding background
conditions has priority.
Christmas shutdown: end of beam operation 21.12.2001 07:00hrs, interlocks
set/start beam operation 16.01.2002
Access days: first Tuesday of every month
Two days of machine studies (4 shifts + 1 shift setup for collisions) every
week until end of April.
Probably no machine studies at the end of the running period.
Switch to electron beam operation in May 2002.
The rotator positions will probably be changed once per month.
The present plan is to run until at least November 2002, depending on
the available manpower (HERA shift personnel). A shutdown of 3 months is
required to install the H1 Very Forward Proton Spectrometer.
Discussion on switching to electrons
Three dates for switching to electron beam operations were discussed:
Christmas break 2001/2002
This could be the most efficient way to switch to electrons. It is
however important to have a thorough understanding of the electron
machine including background conditions with positron beam.
Spring 2002 (favored by ZEUS)
This would enable the machine group to have a good understanding of
the electron machine with positron beam operation. The switch-over
should be done after high luminosity operation is achieved, as agreed
in the last HERA coordination meeting in May 2001. A rough
time estimate for this is April 2002. Since there is some lead time
required to do the shift-over, the date should be fixed and should
include some time for possible delays, i.e. shift over in May 2002.
Winter shutdown 2002/2003 (favored by H1).
This would maximize the integrated luminosity (e+ p collisions) in
2002. Possible problems with electron beam operation would, however,
only be recognized in 2003.
There was no agreement between the experiments on the shift-over date.
ZEUS preferring to take electron data as soon as possible, in order to
quickly increase the e- p data sample. H1 favoring maximum integrated
luminosity with positrons to present a first result on electroweak physics
from the upgraded HERA for the summer conferences 2002. HERMES favoring
maximum integrated luminosity regardless of the lepton charge.
In the end, Robert Klanner proposed to change to electrons in May 2002
and to decided this in the meeting of the directorate.
Since the meeting the date of the switch-over date has been defined as May
20. 2002 and approved by the directorate.
Date of next meeting
The date of the next meeting is Monday, 13.05.2002 10:00hrs
Uwe Schneekloth