HERA Experiment Coordination Meeting
Friday, 12.01.2001 __________________________________________________________
Agenda
- Status and schedule of shutdown activities (critical items)
- Plans and schedule for HERA startup
- Date of next meeting
- AoB
Presentations
Summary of meeting on background and radiation monitoring, U. Schneekloth
See minutes of
meeting
HERA, F.Willeke transparencies (ps),
transparencies
(word)
H1, E.Elsen transparencies
ZEUS, B.Foster transparencies
B.Loehr: Shutdown activities transparencies
, schedule transparencies
HERMES, J.Stewart transparencies
HERA B, K.Ehret transparencies
End of Shutdown
The end of the ZEUS shutdown is delayed by about 3 weeks (detector
closed 25.06.2001). The
implications on the HERA startup are not yet clear.
Some of the HERA activities are a few weeks late. The impact on the
schedule is still unclear.
The final end of the shutdown will be fixed in a special meeting of
the spokes persons, HERA
and directorate Monday 12.02.2001.
The next meeting is Monday, 14.05.2001 11:00hrs seminar room 1.
Uwe Schneekloth